15 January | residential

SKY Residences - A new year brings big things

We're already one third of the way down!

There was no rest onsite over the holiday period. Alright maybe a little.  Don't be fooled though there has been plenty of progress. In December we began the excavation of approx. 30,000 tonnes or 17,000m3 of soil from the basement. We're now one third of the way down!

The Basement CSM retaining wall was completed when the Perimeter Capping Beam was set and finished. The temporary anchors that help hold the wall in place have been drilled and placed, ready for completion this week. Also, this week we'll see the dewatering spear system installed and commissioned, essential for keeping water from within the pit. Relocation of the sewer, gas and water services is underway and the final site amenities are in place. Down we go!

WHAT'S BEEN HAPPENING ONSITE;

  • Services relocations underway
  • Final site amenities set-up
  • Basement CSM retaining wall works complete
  • Perimeter capping beam complete
  • Excavation dewatering spear system installed and being commissioned
  • Temporary anchors nearing completion
  • Basement excavation commenced, currently at 1/3 of depth

To learn more about SKY Residences < CLICK HERE >


Sign up for our newsletter

Enjoy a backstage pass to upcoming projects developments and more.

Thank you for contacting GWH. We will be in touch shortly.